During the recent heat wave in Texas, the Electricity Reliability Council of Texas (ERCOT), the operator of the electric grid covering most of the state, set a new record for electricity use when demand for electricity reached 69.8 gigawatts (GW) between 4:00 p.m. and 5:00 p.m. on August 10. ERCOT has been able to handle this extremely high demand without any system emergencies.
In its summer 2015 reliability assessment, the North American Electricity Reliability Corporation (NERC) had forecasted a pushed peak demand higher than forecast, the grid has performed as expected.
In August 2011, in ERCOT.
Unlike all other U.S. regional transmission organization wholesale electricity markets, ERCOT has neither a capacity market nor a requirement that energy suppliers build or purchase reserve capacity to meet unexpected supply shortages. Instead, ERCOT allows wholesale prices to rise relatively higher than in other markets during system emergencies. This encourages consumers to conserve energy while relying on high wholesale electricity prices to spur investment in generation resources.
Price caps are instituted in wholesale markets so that generators cannot charge unreasonable prices when power is scarce. from overcharging during system emergencies. ERCOT day-ahead zonal prices were near $ 2,250/MWh during the hour of greatest demand on August 10.
ERCOT has taken additional price-related actions to encourage investment in generation. These actions include adding a premium to real-time prices when resources are scarce based on the outage risk and the lost value to consumers of an outage, establishing price floors for emergency response services to keep prices from falling during emergencies, and allowing generators to earn a capacity price for reserving a limited amount of capacity to provide ancillary services.
ERCOT has also added more generating capacity and demand response. Since last year’s NERC summer assessment, more than 6 GW of new generating capacity, mostly natural gas and wind, has been installed in ERCOT. Year-to-date through August 11, Texas used a to help fuel the state’s expanded power generation needs. ERCOT also has several types of demand-response programs that allow participants to bid in a price for either voluntarily using less electricity or by running distributed generation resources. Together these demand-response programs represent 3.4% of the ERCOT total internal demand forecast.